← Home

Welcome Back

Sign in to your Ask SURI account

Project Config

Projects
Select a project to view configuration
Dashboard
Ask SURI
Schedule & Logic
Project History
SURI Updates
Schedule Review
Delay Analysis
Linear Schedule
Executive Summary
SCHEDULE SNAPSHOT
--
Activities
--
--
Critical
zero float
--
In Progress
--
--
Complete
--
--
Time Elapsed
--
Key Dates Start -- | Data Date -- | Finish -- | Duration -- | Elapsed -- | Remaining -- Schedule Quality ▼
Resource Loading
Schedule Intelligence
Ask SURI
Response Depth:
Risk Report Critical Path Longest Path Lookahead Neg Float Logic Gaps Behind Schedule Long Duration Constraints Float Dist. Earned Value Milestones Health Check WBS Tree Search Activities ⚡ What-If
Tip: Ask "What if [activity] takes X more weeks?" or "What if we add a link between A and B?" to run scenario analysis
Linear Schedule
Station:
Scroll to zoom · Click + drag to pan · Double-click to reset
Monthly Schedule Review

Schedule Review

Your monthly check of the contractor's submission against the contract. Resource & cost integrity, required milestones, schedule compliance, narrative coverage, and claim verification — all in one report. Every finding cites evidence so you can challenge it confidently.
Contract milestones

Required Milestones

Paste milestone text in any format (natural language, table, list), upload Excel/CSV/DOCX/PDF, or add one at a time. SURI parses names + target dates + criticality automatically.
Audit Inputs

Schedule + Narrative

Is this audit reviewing a contractor RESUBMITTAL (R1 or later)?
Click Run Audit to start. The Scope panel on the right shows which checks will run based on your inputs.

Delay Claims

Build, analyze, and document delay claims for this project
Loading claims...
Gantt
Network
+
Flatten:
STEP 1 Active
Progress As Of
Advancing the data date creates a new versioned schedule copy
Pick a new data date and click Change Data Date. SURI saves the current schedule and creates a copy named ProjectName_DDMMMYYYY_SURI at the new date. The current schedule stays intact in your Projects list. To fix activities without advancing the data date, commit corrections in the sections below — no copy is made.
Current Data Date: --
STEP 2 · OPTION A Pending
Quick Update
Update activities using natural language
Type commands like: "A1010 started March 1, 75% done, 5 days remaining"  |  "Mark bridge deck pour complete, finished last Friday"  |  "Set remaining duration to 10 days for A2050"
In Progress Should Have Started Finishing Soon % Complete
Data Date: -- Change Latest Actual Start: -- Latest Actual Finish: -- -- ✓ Schedule auto-runs after every commit
Ready to accept schedule updates via natural language.
STEP 2 · OPTION B Pending
Update Schedule
Bulk update via Excel template
1. Export Template

Download an Excel sheet with all in-progress and upcoming activities. Fill in actual dates, percent complete, and remaining durations.

2. Upload Updates

Upload any Excel with Activity ID, dates, % complete, and remaining duration. SURI auto-detects columns — works with templates or your own spreadsheets.

📄
Drop .xlsx file here or click to browse
STEP 4 Pending
Out-of-Sequence
Find and fix sequence violations
STEP 5 · EXPORT Pending
Export Schedule
Re-export as XER for P6 re-import
This export contains the updated working schedule only. Baselines in P6 are not affected by re-import. Use "Update Existing Project" in P6 to merge changes back into your live schedule.
STEP 5 · NARRATIVE Pending
Schedule Narrative
Generate update narrative for owner reporting
Reporting Period
Loading comparison options...
Compose Narrative
Standard sections
Custom focus areas
Brand Settings (Logo, Colors, Company Name)
Agency Narrative Requirements

Upload your agency's narrative specification (.pdf, .docx, .txt). SURI parses it once and stores it for the project — you don't need to re-upload on each update or after a refresh.

Look-Ahead
Flatten:
Schedule Change Log